Dua Paket Pengerjaan Zona Nol Telah Mencapai Lebih Dari 50 Persen

PD. PAL Jaya Completes 7 Pipeline Network Construction Packages at Zone 0

PD. Wastewater Management (PAL) Jaya has completed 7 of 9 pipeline network construction packages at Zone 0 in Jl. Jenderal Sudirman, Manggarai, SCBD, Jl. Gatot Subroto and Jl. HR. Rasuna Said.

The one that located on Jl. Asia Afrika has reached 75 percent for its construction

PD. PAL Jaya Administration and Finance Director, Sigit Suryanto said, pipeline network construction in Zone 0 has been started since 2018. There are two pipeline network construction packages that haven't finished yet which located on Jl. Asia Afrika and Jl. Jenderal Sudirman Timur.

"The one that located on Jl. Asia Afrika has reached 75 percent for its construction. It starts from the former Taman Ria to Plaza Senayan for about 5 kilometers. Currently, we are still working on microtunneling or making a small tunnel using underground drilling machine. Our target is to finish it in the next two or three months," he mentioned, Wednesday (8/12).

PD. PAL Jaya Cleans Up Manhole in SCBD

Meanwhile for construction on Jl. Jenderal Sudirman Timur has reached 55 percent and currently it is on the process of microtunneling.

Delay in those two packages, especially for Sudirman Timur package was due to Asian Games and Asian Para Games events. His side got the permission to continue the pipeline network construction on October 2019.

"We need to do the construction carefully, especially in Sudirman Timur, because there are MRT and neat sidewalks. It makes the construction becomes more complicated. Thus we target it to finish next year," he conveyed.

Meanwhile, the other 7 construction packages in the south and north sides of Jl. Gatot Subroto have been completed in last April.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1578 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1437 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1301 personFolmer
  4. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1094 personNurito
  5. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye965 personDessy Suciati